Central Roadway Layby

Completed January 2019

£6,000

Trumpington Street

 

Funded by Department

Relocation of motorcycle parking to outside old Structures Lab, and creation of layby opposite Stores in the central roadway to impove traffic flow and safety on site.

 

Staff Kitchen Extension

Completed January 2019

£35,450

Electrical Engineering

13m2

Funded by Department

Extension and fit-out of existing staff tea-room into larger staff kitchen including the installation of kitchen cabinets and worktop counters within. Relocation of deli-bar and services to provide required space to accommodate the kitchen extension.

 

Male WC Refurbishment

Completed April 2019

£30,800

First floor, Baker Building

 

Funded by Department

Strip out and refurbishment of existing toilet to create a modern facility with increased occupancy use. Extension into library cupboard to maximise WC space.

 

Laminar Flow Cabinet

Completed June 2019

£38,500

Nanoscience

 

Funded by Department

Laminar flow cabinet extension: removal and manufacture/installation of larger area laminar flow cabinet with connections to house Nitrogen supply and bottle Argon.

 

Chemical Storage

Completed July 2019

£8,500

Nanoscience

 

Funded by Department

Installation of a secure chemical storage compound and relocation of bike racks to accommodate the installation.

 

Cleanroom Modifications

Completed August 2019

£16,000

Nanoscience

 

Funded by Department

Reconfiguration of existing bio-lab to create an additional smaller lab.

 

Baker Common Room

Completed August 2019

£574,000

Trumpington Street, Baker Building

2,899m2

 

Funded by University of Cambridge + Department

The strip out and refurbishment of the existing common rooms to create an open, naturally lit and modern space for staff and students to congregate during mealtimes/breaks. Relocation and refurbishment of the existing boardroom.

 

IFM Common Room Refurbishment

Completion September 2019

£40,000

IFM

 

Funded by Department

Refurbishment of staff kitchen area, replacement of white goods, and kitchen worktops.